Main bonding jumper, system bonding jumper, equipment bonding jumper. The three names sound almost the same, and exam writers know it. The good news is that you can separate them with one question: where is the jumper, and what is it joining? This guide compares the three side by side so you can answer the definition questions quickly and avoid the usual mix-ups.

Start with the shared idea

A bonding jumper is a conductor that connects metal parts or conductors so they are electrically joined. The Article 100 definition quoted in a trade-magazine glossary describes it as a conductor properly sized in accordance with Article 250 (EC&M, Grounding and Bonding Definitions). The three names tell you the job and the location. The size and the exact installation rules come from Article 250 in your adopted edition.

The three jumpers side by side

JumperWhat it joinsWhere it is used
Main bonding jumperThe grounded (neutral) conductor and the equipment grounding conductorAt the service equipment
System bonding jumperThe grounded conductor and the equipment grounding side, with the same job as the main bonding jumperAt a separately derived system
Equipment bonding jumperTwo or more portions of the equipment grounding conductorWherever the equipment grounding path needs to be connected

The wording of the definitions changes a little between code editions, so use the table as a memory aid and read the exact text in your own code book.

Main bonding jumper

The main bonding jumper is the link at the service. One glossary describes it as the connection between the grounded circuit conductor and the equipment grounding conductor at the service (City of Salinas grounding and bonding fact sheet). It is installed at the service equipment, with the installation rules in 250.24(B) (EC&M). It can be a wire, a screw or a strap, depending on the equipment.

The fact sheet notes that the minimum size of the main and system bonding jumpers comes from Table 250.102(C)(1), and that when a service has more than one enclosure with a disconnecting means, each enclosure is considered separately for sizing.

System bonding jumper

The system bonding jumper does the same kind of job for a separately derived system. It is installed under 250.30(A)(1) (EC&M). The point of the connection is to give ground-fault current a low-impedance path back to its source so the overcurrent device can open. The fact sheet adds a location rule worth remembering: the system bonding jumper can be placed at the source enclosure or in the first disconnecting means or panelboard, but not both.

Equipment bonding jumper

The equipment bonding jumper is different in kind. It does not tie the neutral to anything. It connects two or more portions of the equipment grounding conductor, so the equipment grounding path stays continuous. The definition is the same in both of the sources checked for this article (Salinas fact sheet and Electrical Engineering Portal).

Where does the supply-side bonding jumper fit?

You will also meet a fourth name. A supply-side bonding jumper is described as a conductor installed on the supply side of a service or within the service equipment enclosure, or on the supply side of a separately derived system (Electrical Engineering Portal). Its size is based on the ungrounded conductors it serves, so a question about parallel raceways may ask you to size one per raceway. Keep it separate in your notes from the main bonding jumper, even though the names are close.

Three questions that sort the jumpers

  1. Is it at the service? If it joins the grounded conductor to the equipment grounding conductor there, it is the main bonding jumper.
  2. Is it at a separately derived system? Then it is the system bonding jumper.
  3. Is it just bridging parts of the equipment grounding conductor? Then it is an equipment bonding jumper.

Common mix-ups

  • Calling every jumper a "ground wire." The three jumpers have different jobs and different locations.
  • Putting the system bonding jumper in two places. The source says one location, not both.
  • Confusing the equipment bonding jumper with the main bonding jumper. Only the main one ties the grounded conductor to the equipment grounding conductor at the service.
  • Mixing up the main bonding jumper and the supply-side bonding jumper. The supply-side one is sized from the ungrounded conductors it serves.

A quick self-check

A separately derived system needs its grounded conductor tied to the equipment grounding side. Which jumper does that? The system bonding jumper. If you said main bonding jumper, check the location: the main bonding jumper belongs to the service equipment, not to a separately derived system.

Read the real code

Definitions and section numbers shift between editions, and some of the sources quoted here describe earlier editions. Always check the article text in the edition your state has adopted, and ask your authority having jurisdiction (AHJ) for installation questions. The National Fire Protection Association publishes NFPA 70 with free online access at nfpa.org. CircuitDrill is an independent study tool and is not affiliated with NFPA or the NEC.

Keep practicing

For more exam-style practice, see the CircuitDrill course, and compare this topic with the guide on EGC versus GEC sizing.

Frequently asked questions

What does the main bonding jumper connect?

It connects the grounded (neutral) conductor and the equipment grounding conductor at the service equipment. Installation rules are in 250.24(B).

How is a system bonding jumper different from a main bonding jumper?

It does the same kind of job, but at a separately derived system such as a transformer secondary, under 250.30(A)(1), rather than at the service.

What is an equipment bonding jumper?

It connects two or more portions of the equipment grounding conductor so the equipment grounding path stays continuous. It does not tie the neutral to anything.

Can the system bonding jumper be installed at both the source and the first disconnect?

One source describes the location as either the source enclosure or the first disconnecting means or panelboard, but not both. Confirm the rule in your adopted NEC edition.